[torqueusers] Question to Torque community regarding display of completed jobs in qstat
Christopher Samuel
samuel at unimelb.edu.au
Mon Dec 10 16:18:11 MST 2012
-----BEGIN PGP SIGNED MESSAGE-----
Hash: SHA1
On 06/12/12 03:57, Craig Tierney - NOAA Affiliate wrote:
> This is exactly what I want to do. But that requires setting
> keep_completed_jobs to 86400. This means I will have 30000+ jobs
> in completed state, slowing down the response of qstat (and I doubt
> people want to see the completed jobs most of the time). Hence the
> point of this discussion.
For what it's worth I think we'd be fine with qstat doing the
filtering, but not with altering the API to not return completed jobs
(and hence cause issues for Maui/Moab and anything else that talks to
the pbs_server that way).
cheers,
Chris
- --
Christopher Samuel Senior Systems Administrator
VLSCI - Victorian Life Sciences Computation Initiative
Email: samuel at unimelb.edu.au Phone: +61 (0)3 903 55545
http://www.vlsci.org.au/ http://twitter.com/vlsci
-----BEGIN PGP SIGNATURE-----
Version: GnuPG v1.4.11 (GNU/Linux)
Comment: Using GnuPG with undefined - http://www.enigmail.net/
iEYEARECAAYFAlDGbbIACgkQO2KABBYQAh90VwCfWVFiOuq6cnMS5msYnLBIxp6G
ggAAmwb5xkD4ILLDoFJvX8lwv0p7kqdK
=2YED
-----END PGP SIGNATURE-----