[torqueusers] Hogging Nodes
Sarah Mulholland
smm at rincon.com
Wed Mar 18 17:47:46 MDT 2009
I sent this question to the maui group over a week ago, but there was no answer. Perhaps this question is more appropriate to the torque group.
I am running the maui scheduler 3.2.6 patch level 16 with torque 2.1.6. I am looking for a way to submit a job on some number of nodes, say 10. In addition to running on 10 nodes, I want exclusive use of those nodes. Is there a property I can set to allow that kind of scheduling? So far I'm submitting jobs with
"-l nodes=10:ppn=1"
Specifically I have a job that needs to run on 10 processors all on different nodes. We have two processors per node. The JOBNODEMATCHPOLICY EXACTNODE makes sure our job gets what it needs, but I want to prevent anything else from running on the second processor of the 10 nodes.
Is there a "don't-share-the-nodes" modifier that I can set on the job submission? In the maui.cfg?
Thanks
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://www.supercluster.org/pipermail/torqueusers/attachments/20090318/076c89e9/attachment.html
More information about the torqueusers
mailing list