[torqueusers] torque only assigns one node

asubedi asubedi at gmail.com
Sat Feb 9 01:27:12 MST 2008


I am trying to use "#PBS -l nodes=3" in my job script to run a job in
three nodes. However, torque only assigns one node. However, If I do
"#PBS -l nodes=node001+node002+node003", it assigns those three nodes.
Does anyone know what am I doing wrong? The output of qmgr -c 'p s'
is:

#
# Create queues and set their attributes.
#
#
# Create and define queue long
#
create queue long
set queue long queue_type = Execution
set queue long Priority = 60
set queue long max_running = 60
set queue long resources_max.cput = 96:00:00
set queue long resources_max.ncpus = 20
set queue long resources_max.nodect = 20
set queue long resources_max.nodes = 20
set queue long resources_min.cput = 02:00:01
set queue long resources_default.cput = 96:00:00
set queue long enabled = True
set queue long started = True
#
# Set server attributes.
#
set server scheduling = True
set server max_user_run = 100
set server managers = root at head.funmatcluster
set server operators = root at head.funmatcluster
set server default_queue = default
set server log_events = 63
set server mail_from = adm
set server resources_available.nodect = 999999
set server resources_default.cput = 01:00:00
set server resources_default.nodect = 4
set server resources_default.nodes = 4
set server scheduler_iteration = 60
set server node_ping_rate = 300
set server node_check_rate = 600
set server tcp_timeout = 6
set server default_node = 100
set server mom_job_sync = True
set server pbs_version = 2.2.1
set server keep_completed = 300


More information about the torqueusers mailing list