David Sheen wrote:
> Good morning, everyone.
>
> I am currently running a cluster with 8 dual-core nodes with TORQUE
> and Maui. As TORQUE is currently set up, if I submit (say) 16 jobs to
> the cluster, then 8 of them start executing and the other 8 go into
> the queue. How do I tell TORQUE (or possibly Maui?) that it is OK for
> there to be two (or possibly more?) jobs allocated to a given node?
>
> Thanks!
>
> David Sheen
> _______________________________________________
> torqueusers mailing list
> torqueusers at supercluster.org
> http://www.supercluster.org/mailman/listinfo/torqueusers
set the np parameter for each node in the
/var/spool/torque/server_priv/nodes file
atlas np=2
zeus np=32
--
James A. Peltier
Technical Director, RHCE
SCIRF | GrUVi @ Simon Fraser University - Burnaby Campus
Phone : 604-291-3610
Fax : 604-291-3045
Mobile : 778-840-6434
E-Mail : jpeltier at cs.sfu.ca
Website : http://gruvi.cs.sfu.ca | http://scirf.cs.sfu.ca
MSN : subatomic_spam at hotmail.com
More information about the torqueusers
mailing list